Contract structures
Fixed-price is the most common and most owner-protective structure. The GC commits to a total price; the risk of cost overruns is theirs (subject to change-order terms). For most projects at this size, fixed-price is what you want.
In a fixed-price contract, the GC's markup on subcontractor costs (typically 15–20%) is baked into the lump-sum number, not broken out as a separate line. That's not deceptive — it's the model. The GC commits to the price; the markup covers project management, overhead, warranty, and profit; the risk of subcontractor cost overruns is now their problem, not yours. The question isn't whether the markup exists (it always does) — it's whether the lump-sum is competitive against the other bids.
Cost-plus (GC's actual cost + a percentage markup, typically 5–20%) can work, but only with a guaranteed maximum price (GMP) cap and weekly itemized invoices. Without a cap, cost-plus puts all the budget risk on you; the cap is what makes the structure work.
Guaranteed Maximum Price (GMP) mixes the two: GC bids a not-to-exceed price, with shared savings if the actual cost comes in below.
What the contract must include
- Scope of work in detail (reference the permit-ready set by date and revision number).
- Payment schedule tied to milestones, not a calendar.
- Change-order process — written approval required, rate sheet for hourly labor, markup percentage on materials.
- Schedule — substantial completion date, liquidated damages if applicable.
- Allowances — cabinets, flooring, fixtures, appliances, with itemized values.
- Exclusions — explicit list of what's NOT in the bid (often: landscape, decks, utilities beyond connection point, finish upgrades).
- Warranty — at least 1 year workmanship; longer for specific systems.
- Lien waivers — conditional and unconditional, on each progress payment and at completion.
- Dispute resolution — mediation before arbitration before litigation, in WA.
When to hire an attorney
For contracts over about $300,000 — which is most Seattle DADUs — an attorney review of the contract pays for itself. Two to six hours of focused review at $400 – $650/hr in Seattle ($1,000 – $4,000 total) catches the change-order terms and lien-waiver schedule that decide how the project handles surprises.
This is informational framing; HomePlan does not provide legal advice. Verify any attorney via the Washington State Bar Legal Directory.
Where to find a construction-savvy attorney
Three reliable channels:
- WSBA Legal Directory (search) lets you filter by practice area — "Construction Law" or "Real Estate" cover most attorneys handling residential renovation contracts.
- Your designer or GC's recommendation. Designers and GCs at this scale have usually worked with an attorney on a prior review; they know who understands construction vocabulary.
- Referral from another professional. A real-estate attorney you've used before may refer to a colleague who handles construction contracts.
What to look for: experience reviewing residential construction contracts at your project's value range; flat-fee or capped-hourly (not contingency); willingness to flag change-order, hidden-condition, and lien-waiver language specifically.
Initial deposit
10% is a common ask; 5% is more conservative. Stage subsequent payments to milestones (foundation, framing, MEP rough, drywall, substantial completion). Each milestone payment trades dollars for verifiable progress — that's how you protect yourself against builder-side problems mid-project.
Go deeper
Optional reading. Skip if you only need the headline.
›Mechanics' lien deadlines and waiver procedure (WA, 90-day window)Three working parts of WA construction-lien procedure: a 90-day filing window, a pre-claim notice rule for subs, and a two-stage statutory waiver schedule that runs alongside payments.
The procedure in three parts
Washington's construction-lien procedure under RCW 60.04 has three working parts that operate together:
- A 90-day filing window measured from the last day labor or materials were furnished.
- A pre-claim notice that subs and suppliers (not the prime GC) have to deliver early in their work.
- A two-stage waiver schedule — conditional waivers at each progress payment, unconditional final waivers at completion — using statutory forms in RCW 60.04.071.
Anyone who furnishes labor or materials to an improvement on your property — GC, sub, supplier — has lien rights under the chapter. Liens are recorded with the King County recorder and stay on title until released. The waiver schedule is how lien rights get released as payments flow through.
The 90-day clock
A claimant has 90 days from the date they last performed labor or supplied materials to record the lien. After 90 days with no recording, the lien right expires.
For a Seattle DADU: substantial completion isn't the all-clear. Title is fully clear 90 days after the last sub leaves the site — usually the landscape, paving, or punch-list crew, not the GC.
Pre-claim notice (RCW 60.04.031)
For most subs and material suppliers (not the GC you contracted with directly), the lien right depends on first delivering a pre-claim notice to you within 60 days of starting work or supplying materials. Getting one of these during construction is routine — it's a procedural protection, not a dispute. Treat it as a signal that the sender is on the property and add them to the waiver list for upcoming draws.
The lien waiver schedule
Two waivers, two stages:
| Waiver type | When | Who signs | What it does |
|---|---|---|---|
| Conditional waiver upon progress payment | At each progress payment | GC + every sub/supplier on that draw | Releases lien rights conditional on the check clearing. Standard practice. |
| Unconditional waiver upon final payment | At final payment | GC + every sub/supplier who worked the project | Releases lien rights absolutely. Get this from everyone before final disbursement. |
Both forms are statutory in WA — RCW 60.04.071 prescribes the conditional/unconditional progress and final waiver language. Use the statutory form so it survives challenge.
How to operate the schedule
- In the GC contract, require a current sub list with each progress draw.
- For each progress draw, the GC delivers (a) signed conditional waivers from every sub/supplier on that draw plus (b) a signed conditional from the GC for their own scope. The bank/lender disbursement is conditioned on receipt.
- At final payment, switch to unconditional final waivers from every sub and supplier who appeared on any draw, plus unconditional final from the GC. Hold final retainage until all are received.
- Then run the 90-day clock anyway. Even with full waivers, monitor the King County recorder for liens for 90 days from the last on-site work. Recording a lien against a fully-waived project is rare but happens.
When this matters most
- Cost-plus contracts without a tight waiver schedule. You pay the GC, the GC pays subs late, subs record liens. You've paid in full and still have clouded title.
- Refinancing or selling within a year of completion. Title companies ask about pending or recently-released liens. A clean waiver file at handoff makes it a 10-minute conversation.
- Bankruptcy of the GC during the project. Subs paid through the GC may not have been paid; their lien rights are against your property, not the GC's bankruptcy estate.
Informational framing
This is general information about Washington lien procedure. It's not legal advice and doesn't establish an attorney-client relationship. For waiver language specific to your contract, or if you receive a recorded lien, consult an attorney licensed in WA — verify via the WSBA Legal Directory.
Sources for this section
- RCW 60.04 — Mechanics' and materialmen's liens (Washington State) · retrieved April 23, 2026
- RCW 60.04.071 — Statutory waiver of lien forms (conditional / unconditional, progress / final) · retrieved April 23, 2026
- RCW 60.04.091 — Recording requirements and 90-day filing deadline · retrieved April 23, 2026
›Splitting scope between your GC and trades you hire directly (Separate Contractors, WA)What the standard contract frameworks call 'Separate Contractors,' how each owner-direct trade becomes its own lien claimant under WA law, and what to address in the GC contract before you sign.
What this is
A Seattle DADU is almost always built single-prime: one GC, every trade flows through them, one chain of accountability. The alternative — sometimes called "Separate Contractors" or "multi-prime" — is when you keep the GC for the main build but contract directly with one or two trades yourself.
For a DADU, the natural carve-outs are narrow:
- Appliances — buy direct (often via a builder-supply account or end-of-season sale) and have the GC install. This is the classic "Owner-Furnished, Contractor-Installed" pattern.
- Finish hardware — cabinet pulls, lighting fixtures, plumbing fixtures procured directly and handed to the GC.
- Post-CofO landscaping — your usual landscape contractor, after the Certificate of Occupancy clears.
What you do not carve out on a DADU: the side-sewer trench, the SCL energization coordination, the MEP rough trades, or anything that has to interleave with the GC's permit-bearing build. Those have to flow through the GC.
How the standard contracts handle it
AIA A201-2017 Article 6 (overview) calls them "Separate Contractors" — the owner has the right to award separate contracts, the GC and the Separate Contractors must coordinate, and the GC can claim added cost or time if a Separate Contractor's work damages or delays theirs. ConsensusDocs 200 §3.12 (product page) has equivalent language. The framework exists; that's why the practice is possible.
The four real costs
- Warranty seams. When the owner-sourced dishwasher leaks 18 months in and warps the GC's flooring, the GC will say "not my fixture" and the appliance vendor will say "not my install" — and you pay twice. The canonical write-up is Markup & Profit's Owners Supplying Their Own Materials.
- Coordination duty shifts to you. A201 places the coordination duty on whoever is contracting with both parties — which is you. Schedule the appliance delivery wrong and the cabinet install slips a week.
- Insurance gap. The owner-sourced trade's CGL policy doesn't automatically name you as additional insured, and the GC's policy almost certainly excludes work it didn't control.
- Multiple independent lien exposures. This is the WA-specific one — see the next section.
What WA lien law adds
Every trade you contract with directly becomes its own "prime contractor" with full lien rights against your property — not a sub-tier claim that flows up through the GC. That's true everywhere. What's specific to WA is the no-notice path.
Under RCW 60.04.031(3)(a), persons who contract directly with the owner-occupier of an existing single-family residence for repair, alteration, or remodel are exempt from the pre-claim notice requirement that applies to subs and suppliers in the GC's chain. Each owner-direct trade can record a lien against your house without ever sending you the "Notice of Right to Claim a Lien" you'd get from a sub working under the GC.
Note that a DADU is a new structure, not a repair / alteration / remodel of the existing main house — so for trades whose work touches only the DADU footprint, the (3)(a) exemption arguably doesn't apply. The cautious read: assume each owner-direct trade has full lien rights, run the waiver schedule as if they do, and let an attorney confirm if the project shape makes a difference.
On the disclosure side: every contractor (each owner-direct trade included) doing residential work of $1,000 or more must give you the statutory disclosure statement before starting under RCW 18.27.114. Subsection (4): a contractor who didn't deliver the disclosure can't bring a lien claim. So one defensive practice is to require the disclosure on every direct trade before any payment.
What to address in the GC contract before you sign
Most homeowners ask a construction-savvy attorney to review these areas with them — most are in A201 §6 or ConsensusDocs 200 §3.12 if you're using those templates, and have to be added as a custom rider if you're using AIA A105 (which doesn't incorporate A201's Separate Contractors framework at all):
- Carve-out list. Name the specific scopes you reserve the right to contract separately (appliances, landscape after CofO). What's not on the list flows through the GC.
- Coordination duties. Who schedules, who notifies whom, what happens if an owner-sourced delivery misses its window.
- Damage attribution. A201 §6.2.3 gives the GC cost/time relief for Separate Contractor damage; mirror that for owner-direct trade damage to GC work.
- Insurance. Owner-sourced trades' CGL must name the homeowner as additional insured before they show up.
- Lien-waiver flow. Each owner-direct trade signs into the same conditional/unconditional waiver schedule the GC uses (see the previous expansion).
- No-markup acknowledgement. GC isn't responsible for warranty on owner-sourced equipment or installs.
Verify any attorney via the WSBA Legal Directory. Two to four hours of focused review on this section is typical.
When this is worth doing
On a DADU at $400K–$650K, the realistic carve-out limit is one or two narrow items — appliances, finish hardware, post-CofO landscape. Beyond that, the savings get eaten by coordination time, warranty fights, and the per-trade lien-waiver overhead.
If you're tempted to direct-hire more than two trades on a DADU, you're heading toward owner-as-GC, which is a different workflow and requires a different contract structure (and probably a different insurance posture). Most owners are better served by negotiating allowances inside the GC contract for the line items they care about, rather than carving them out.
Informational framing
This is general information about how the standard contract frameworks and WA lien law treat owner-direct-contracted trades. It is not legal advice and does not establish an attorney-client relationship. For language specific to your contract, consult an attorney licensed in WA — verify via the WSBA Legal Directory.
Sources for this section
- AIA — Who Are the Owner's 'Separate Contractors'? (A201-2017 Article 6 overview) · retrieved May 25, 2026
- ConsensusDocs 200 — Owner and Constructor Agreement (Lump Sum) — §3.12 covers owner's right to award separate contracts · retrieved May 25, 2026
- Markup & Profit — Owners Supplying Their Own Materials · retrieved May 25, 2026
- RCW 60.04.031 — Pre-claim notice (subsection (3)(a) exemption for owner-occupier direct contracts on existing single-family residences) · retrieved May 25, 2026
- RCW 18.27.114 — Residential contractor disclosure statement (required at $1,000+; failure forfeits lien rights) · retrieved May 25, 2026
Where this information came from
- SDCI Tip 116B — Establishing a DADU · retrieved April 22, 2026
- Building Connections — Side sewer transfer to SPU · retrieved April 22, 2026
- King County Wastewater Capacity Charge · retrieved April 22, 2026
- L&I Verify a Contractor · retrieved April 22, 2026