Sequence
- Cabinets installed — kitchen first, then bathrooms and built-ins.
- Counter template — fabricator measures the actual installed cabinets.
- Counter fabrication — 2–4 weeks off-site.
- Counter install — slabs delivered, set, seamed, caulked.
- Tile — backsplashes, shower walls, bathroom floors.
- Plumbing trim — toilets, sinks, faucets, showerheads.
- Electrical trim — outlets, switches, light fixtures, undercabinet lighting.
- Appliance install — refrigerator, range, dishwasher, microwave, range hood. Plumbed, gassed, vented.
Lead times drive schedule
Cabinets are 6–12 weeks from order to delivery. Counters are 2–4 weeks from template to install. Order cabinets at end of framing; order counters when cabinets are installed.
Allowance true-up
Most owners come in 10–25% over the original allowance budget because finish selection happens in real life with a partner — not against a spreadsheet. Plan for it.
Where this information came from
- City of Renton CASSP Permit Portal · retrieved April 30, 2026
- Renton Municipal Code — Title 4 Development Regulations (Municode) · retrieved April 30, 2026
- Renton GIS Hub · retrieved April 30, 2026
- WA L&I — Verify a Contractor · retrieved April 30, 2026
- EPA — Renovation, Repair and Painting (RRP) Rule · retrieved April 30, 2026
- WAC 296-62-07703 — Asbestos definitions · retrieved April 30, 2026
- Energy Code | SBCC — Washington State Building Code Council · retrieved April 30, 2026
- City Electrical Permits & Inspections — WA L&I · retrieved April 30, 2026
- PSE | Building Project Steps and Applications · retrieved April 30, 2026