What happens
The most physically dramatic stretch of the project, in rough order:
- Remove the existing roof — shingles, sheathing, framing. Sometimes done in a single day with a crane and a crew of six; sometimes over a week with a smaller crew.
- Frame the new second-story floor (which becomes the existing first-floor ceiling). New joists span between the existing exterior walls.
- Frame the new second-story walls — bottom plate, studs, top plates, headers, openings. Plumb and square against the variations of the existing first floor.
- Frame the new roof — rafters or trusses, ridge, valleys, eaves. The exterior shape of the addition becomes visible.
- Sheathe walls and roof — with shear panels where the structural engineer requires them.
- Install windows and doors in the new openings.
- Wrap the building with weather-resistive barrier, taped at openings.
- Roof — underlayment, then finished roofing.
By the end of this step, the building is dry-in — weathertight enough that interior trades can work without rain damage.
Inspections
- Framing inspection before insulation. Verifies structural per stamped sheets, fire-blocking, hardware, hold-downs, and the connection of new framing to existing.
- Sheathing nailing inspection on shear panels.
- Window flashing inspection in some cases.
Duration
- 6 weeks for a small simple addition with an experienced crew and good weather.
- 8–10 weeks is the honest range for most Seattle second-story additions, accounting for weather and the inevitable "the existing wall isn't where the as-built said it was" moment.
What goes wrong
- Window delivery. Custom windows have 8–12 week lead times. Order during permit review or framing waits.
- Weather between roof removal and dry-in. This is the big one. A bad November rain on an opened roof is a project-killer. The GC's tarping plan is a contract item, not an afterthought.
- Existing conditions surprises. Rotted sill plate where new load lands. A buried beam not on the as-built. The hidden-conditions allowance in the contract (step 4.3) is what funds the fix without a change-order fight.
Where this information came from
- SDCI — Construction Permit: Addition or Alteration · retrieved April 23, 2026
- SDCI Tip 314 — Substantial Alteration of Existing Buildings · retrieved April 23, 2026
- SDCI Tip 100 — Building Permit Application Submittal Requirements · retrieved April 23, 2026
- L&I — Verify a Contractor · retrieved April 23, 2026
- EPA — Renovation, Repair and Painting (RRP) Rule · retrieved April 23, 2026
- WA Department of Labor & Industries — Asbestos in Construction (WAC 296-62-077) · retrieved April 23, 2026