HomePlan

Phase 1 · Site and existing conditions · Step 1.3

Foundation Assessment for a Seattle Second Story Addition

A licensed structural engineer rates your existing foundation — adequate, needs retrofit ($15K–$60K), or lift-and-replace — in 1–2 weeks for $800–$2,500.

Who
Structural eng.
How long
1-2 weeks
Cost
$800-$2,500
You end up with
Engineer's letter with foundation rating + retrofit recommendation

If you skip this: Foundation is the load-bearing decision for the whole project. Do this assessment before design starts and you can make the lift-vs-retrofit call before paying for full engineering on the wrong assumption.

This is the single most consequential gate on the whole project. The engineer's letter tells you whether the existing foundation can carry a second story, whether it needs a $15K–$60K retrofit, or whether you're in lift-and-replace territory. None of those is bad news — but you need to know which one applies before you spend on full design.

What gets inspected

The engineer looks at:

  • Foundation type — brick-and-mortar, unreinforced concrete, reinforced concrete, post-and-pier.
  • Footing depth and width — exposed at one or two points if not visible.
  • Cracking, settlement, and lateral movement — visual + level readings.
  • Connections to the framing above — anchor bolts (or absence of them), sill condition, hold-downs.
  • Rim joist condition — rot, insect damage, water staining.

What the letter tells you

The engineer issues a short letter with three possible outcomes:

  1. Foundation adequate as-is. Rare for pre-1940 houses; common for post-1980 ones. You can build a second story on the existing foundation with seismic anchor improvements only.
  2. Foundation adequate with retrofit. Most common case. You'll add steel reinforcing, additional footings, or a perimeter beam. Cost typically $15,000–$60,000 depending on scope.
  3. Foundation not adequate. Either build a new foundation under the existing house (with the house lifted on temporary supports — see step 2.2) or accept that this is a teardown-rebuild instead of an addition.

Why you do this in Phase 1, not Phase 2

A second story can't be designed without knowing what's carrying the load. If the engineer's report says "lift required," the design strategy changes substantially — different staging, different schedule, different cost. Better to know now.

Verifying the engineer

Verify any structural engineer through WA DOL license lookup. Ask for two references on Seattle older-home additions and call both.

Where this information came from