Contract structures
Fixed-price is the most common and most owner-protective structure. The GC commits to a total price; the risk of cost overruns is theirs (subject to change-order terms). For a second-story addition, fixed-price is what you want — but with explicit allowances for unknowns inside an old house.
Cost-plus (GC's actual cost + a percentage markup, typically 10–20%) can work, but only with a guaranteed maximum price (GMP) cap and weekly itemized invoices. Without a cap, cost-plus puts all the budget risk on you; the cap is what makes the structure work.
Guaranteed Maximum Price (GMP) mixes the two: GC bids a not-to-exceed price, with shared savings if the actual cost comes in below.
What the contract must include
- Scope of work in detail (reference the permit-ready set by date and revision number).
- Payment schedule tied to milestones, not a calendar.
- Change-order process — written approval required, rate sheet for hourly labor, markup percentage on materials.
- Schedule — substantial completion date, liquidated damages if applicable.
- Allowances — cabinets, flooring, fixtures, appliances, with itemized values.
- Hidden-condition allowances — specific dollar contingencies for known unknowns inside an old house: rotted sills if found, additional knob-and-tube remediation, hidden plumbing repairs. Without these, every discovery becomes a change-order fight.
- Exclusions — explicit list of what's NOT in the bid (often: landscape, decks, exterior paint, finish upgrades).
- Warranty — at least 1 year workmanship; longer for specific systems.
- Lien waivers — conditional and unconditional, on each progress payment and at completion.
- Information Notice to Owner attached — the GC's ION delivery per ORS 87.018.
- Dispute resolution — mediation before arbitration before litigation, in Oregon.
When to hire an attorney
For contracts over about $300,000 — which is essentially every Portland second-story addition — an attorney review of the contract pays for itself. Two to six hours of focused review at $350–$600/hr in Portland ($1,000–$4,000 total) catches the change-order terms, hidden-condition allowance language, and lien-waiver schedule that decide how the project handles surprises.
This is informational framing; HomePlan does not provide legal advice. Verify any attorney via the Oregon State Bar member directory.
Initial deposit
Oregon CCB caps initial deposits at certain percentages depending on the work and the contractor — verify the current cap on the CCB site. 5–10% is conservative and within typical caps for residential general contractor work. Stage subsequent payments to milestones (abatement complete, foundation, framing, MEP rough, drywall, substantial completion). Each milestone payment trades dollars for verifiable progress.
Go deeper
Optional reading. Skip if you only need the headline.
›Construction lien deadlines and waiver procedure (Oregon, 75-day window)Three working parts of Oregon's construction-lien procedure: a 75-day filing window, an 8-business-day pre-claim notice for material suppliers, and a waiver procedure that runs alongside payments.
The procedure in three parts
Oregon's construction-lien procedure under ORS Chapter 87 has three working parts that operate together:
- A 75-day filing window measured from completion of the construction or the claimant's last labor or materials.
- A pre-claim notice that material suppliers and certain subs (not the prime GC) have to deliver early in their work.
- A waiver procedure — conditional waivers at each progress payment, unconditional final waivers at completion — that releases lien rights as payments flow through.
Anyone who furnishes labor or materials to an improvement on your property — GC, sub, supplier — has lien rights under ORS Chapter 87. Liens are recorded with the Multnomah County recorder and stay on title until released. The waiver procedure is how lien rights get released as payments flow through.
The 75-day clock
Under ORS 87.035, a claimant has 75 days to perfect a construction lien — measured from the earliest of:
- The date construction is completed.
- The date the claimant ceased to provide labor or materials.
- The date the owner files a Notice of Completion (which the owner can record under ORS 87.045 to start a 75-day clock).
After 75 days with no recording, the lien right expires.
For a Portland addition: substantial completion isn't the all-clear. Title is fully clear 75 days after the last sub leaves the site — usually the landscape, paving, or punch-list crew, not the GC. Filing a Notice of Completion is the owner's tool to start that clock predictably.
Pre-claim notice (ORS 87.021)
Under ORS 87.021, most material suppliers and certain subs (not the GC you contracted with directly) must deliver a Notice of Right to Lien to the owner within 8 business days of first delivering labor or materials. Without timely delivery, the supplier or sub loses lien rights against your property for those deliveries.
Getting one of these during construction is routine — it's a procedural protection, not a dispute. Treat it as a signal that the sender is on the property and add them to the waiver list for upcoming draws. The notice typically arrives by certified mail or hand-delivered.
The Information Notice to Owner — separate but related
Don't confuse the Notice of Right to Lien (from a sub or supplier, ORS 87.021) with the Information Notice to Owner (from the GC at contract signing, ORS 87.018). Both are statutory and both protect homeowners. The first tells you a specific sub or supplier is on the project; the second is a general explanation of lien procedure that the GC delivers to you once.
The lien waiver schedule
Two waivers, two stages:
| Waiver type | When | Who signs | What it does |
|---|---|---|---|
| Conditional waiver upon progress payment | At each progress payment | GC + every sub/supplier on that draw | Releases lien rights conditional on the check clearing. Standard practice. |
| Unconditional waiver upon final payment | At final payment | GC + every sub/supplier who worked the project | Releases lien rights absolutely. Get this from everyone before final disbursement. |
Oregon doesn't have statutory waiver forms the way California or Washington do — but courts recognize industry-standard waiver language. Your attorney can supply forms; the AGC publishes a commonly-used set.
How to operate the schedule
- In the GC contract, require a current sub list with each progress draw.
- For each progress draw, the GC delivers (a) signed conditional waivers from every sub/supplier on that draw plus (b) a signed conditional from the GC for their own scope. The bank/lender disbursement is conditioned on receipt.
- At final payment, switch to unconditional final waivers from every sub and supplier who appeared on any draw, plus unconditional final from the GC. Hold final retainage until all are received.
- File a Notice of Completion under ORS 87.045 to start the 75-day clock predictably. Then run the clock anyway — even with full waivers, monitor the Multnomah County recorder for liens for 75 days from the last on-site work. Recording a lien against a fully-waived project is rare but happens.
Why this matters more on additions
Additions tend to have more discovered-condition subs (abatement, knob-and-tube remediation, foundation specialists) than new-construction projects. More subs means more pre-claim notices to track and more waivers to collect. Build the schedule into the GC contract from the start.
When this matters most
- Cost-plus contracts without a tight waiver schedule. You pay the GC, the GC pays subs late, subs record liens. You've paid in full and still have clouded title.
- Refinancing or selling within a year of completion. Title companies ask about pending or recently-released liens. A clean waiver file at handoff makes it a 10-minute conversation.
- Bankruptcy of the GC during the project. Subs paid through the GC may not have been paid; their lien rights are against your property, not the GC's bankruptcy estate.
Informational framing
This is general information about Oregon construction-lien procedure. It's not legal advice and doesn't establish an attorney-client relationship. For waiver language specific to your contract, or if you receive a recorded lien, consult an attorney licensed in Oregon — verify via the Oregon State Bar member directory.
Sources for this section
- ORS Chapter 87 — Construction Liens (Oregon) · retrieved April 25, 2026
- ORS 87.021 — Notice of right to lien (8-business-day rule) · retrieved April 25, 2026
- ORS 87.035 — Perfecting a lien; 75-day filing requirement · retrieved April 25, 2026
- ORS 87.045 — Notice of completion by owner · retrieved April 25, 2026
Where this information came from
- Portland Permitting & Development — Residential Permits · retrieved April 25, 2026
- Portland City Code Title 33 — Planning and Zoning · retrieved April 25, 2026
- Portland City Code Title 11 — Trees · retrieved April 25, 2026
- Portland Maps (per-address zoning, hazards, overlays) · retrieved April 25, 2026
- Oregon CCB — Verify a Contractor · retrieved April 25, 2026
- EPA — Renovation, Repair and Painting (RRP) Rule · retrieved April 25, 2026
- Oregon DEQ — Asbestos Program · retrieved April 25, 2026
- ORS Chapter 87 — Construction Liens (Oregon) · retrieved April 25, 2026